Bharat Heavy Electricals Ltd BHEL) has commissioned the second unit (800 MW) of the 2×800 MW Gadarwara Super Thermal Power Project Stage-l.
Located at Gadarwara in Narsinghpur district of Madhya Pradesh, the greenfield project is being developed by NTPC Ltd. The first unit of this project was commissioned by BHEL in 2019 and is presently under commercial operation.
Scope of work
BHEL’s scope of work in the project envisaged design, engineering, manufacture, supply and erection & commissioning of steam turbines, generators, boilers and associated auxiliaries, besides state-of-the-art controls & instrumentation (C&l) and electrostatic precipitators (ESPs).
The key equipment for the project was manufactured at BHEL’s Trichy, Haridwar, Bhopal, Ranipet, Hyderabad, Jhansi, Thirumayam and Bengaluru plants, while the construction of the plant was undertaken by the company’s Power Sector — Northern Region, Noida.
Supercritical equipment
So far, BHEL has commissioned 24 sets of supercritical boilers and 20 sets of supercritical turbine generators of 660/700/800 MW rating, out of which 8 sets of supercritical boilers and 6 sets of supercritical turbine generators have been commissioned for NTPC Ltd.
BHEL has so far contracted 58 sets of supercritical boilers and 53 sets of supercritical turbine generators from various customers, in domestic as well as overseas markets.
(Featured file photograph shows long view of NTPC’s Gadarwara thermal power plant in Madhya Pradesh, whilst under construction.)