Tata Power, in a release, said that it has deployed a unique feature called ‘Mobile-GIS assisted system for Restoration and Care’ (maRC) for its Mumbai customers. It is a digitally automated and cost-effective system for the complete “customer trouble call management” including quality and effective tracking related to power cut or outage complaints.
The pace of addition of 765kV transmission lines slowed down in the first four months of FY22, with the actual achievement standing at only around 16 per cent of the planned target.
According to the latest statistics released by Central Electricity Authority (CEA), the quantum of 765kV lines added in the first four months (April to July) of FY22 was 647 ckm, as against the planned target of 3,949 ckm.