Site icon Your Gateway to Power Transmission & Distribution

Construction work on 765kV Fatehgarh-Bhadla line complete

PGCIL Line | T&D India

For illustration only

 

Construction work on a new 765kV double-circuit line connecting the Fatehgarh-II and Bhadla-II substations in Rajasthan, is complete, and is ready for commissioning.

This line is part of a transmission scheme officially known as “Transmission system associated with LTA applications from Rajasthan SEZ Part-B” is being implemented under the tariff-based competitive bidding (TBCB) route by Power Grid Corporation of India Ltd.

PGCIL won this project in October 2019 and it is being developed through its wholly-owned subsidiary Powergrid Fatehgarh Transmission Ltd (originally incorporated as “Fatehgarh-II Transco Ltd.”)  The project, estimated to cost around Rs.670 crore, aims to evacuate generation from upcoming solar zones in Rajasthan.

Also read: GE Lands Major PGCIL Order For 765kV Transformers And Reactors

The transmission scheme has three components:

 

 

 

The overall project was scheduled to commission by December 2020. As such, it is running behind schedule by at least eight months so far.

 

Background

India has set a target for establishing 175 GW renewable capacity by 2022, which includes 100 GW solar, 60 GW wind generation capacity. To identify ISTS connectivity of renewable energy projects from potential solar energy zones (SEZs) and potential wind energy zones (WEZs) of about 50 GW and 16.5 GW respectively, the Union ministry of new and renewable energy (MNRE), through its order of June 2018, had constituted a sub-committee.

Accordingly, SEZs and WEZs envisaged in seven renewable energy-rich rich states — Tamil Nadu, Andhra Pradesh, Karnataka, Gujarat, Rajasthan, Maharashtra and Madhya Pradesh— were identified by SECI in association with MNRE in consultation with RE power developers.

To ease the implementation of transmission infrastructure, it has been proposed to bifurcate these requirements in two phases. A total of 20 GW solar and 9 GW wind projects has been planned in Phase-I (up to December 2020) and 30 GW solar and 7.5 GW wind has been planned for Phase-II (December 2021).

The implementation of this mega renewable energy evacuation plan is taking place through specific projects, most of them under the tariff-based competitive bidding (TBCB) route.

(Featured photograph for illustration only)

Exit mobile version