Site icon Your Gateway to Power Transmission & Distribution

Hartek Power commissions reactor at PSTCL’s Dhuri substation

 

Hartek Power Pvt Ltd has completed the supply, installation, testing, and commissioning of a 400kV / 125MVAr reactor at the 400/220kV Dhuri substation in Punjab.

Commissioned on March 30, 2023, for Punjab State Transmission Corporation Ltd (PSTCL), the reactor was completed within the stipulated time.

The commissioning of the bus reactor at the 400kV Dhuri substation, along with the construction of an allied bay including the civil work, was a significant achievement for the company, Hartek Power said.

Also read: Hartek Power Wins Order For Underground Cabling In Chandigarh

The company recently commissioned three reactors back-to-back for PSTCL. The first reactor commissioned was the 220kV / 25 MVAr Dhuri plant, followed by the commissioning of the second reactor at the 220 kV / 25 MVAr at the Nakodar plant, and finally, the 400kV / 125 MVAr reactor at the Dhuri plant at PSTCL, Hartek Power said.

Commenting on the successful commissioning, Hartek Singh, Chairman & Managing Director, Hartek Group said, “We are delighted to have completed this project successfully within the timeline. The completion of this project has demonstrated our commitment to providing top-notch services to our clients while adhering to the highest standards of safety and quality. We look forward to continuing our excellent work in the power sector and delivering more projects that meet and exceed our client’s expectations.”

 