Substation capacity addition meets only 43 per cent of target

L&T

Substation capacity addition in the first five months (April to August) of current fiscal year FY25 has met only 43 per cent of the target.

As against 42,230 MVA of substation capacity planned for addition in the April-August period of FY25, actual addition stood at just 18,270 MVA, implying only 43 per cent target achievement.

Here are some more observations:

 

 

Also read: Substation capacity addition in Q1FY25 meets just one-third of target

Note: This story takes into account substations of 220kV or higher only.