“Galvanic Protection Barrier Layer Thickness Test” mandatory for HTLS conductors, says CEA

    The Central Electricity Authority (CEA), in a recent advisory, has said that the “salt spray test” cannot be used as a substitute for the mandatory “galvanic protection barrier layer thickness test” for testing of carbon Read more

ERDA Power Secy LR | T&D India

ERDA officials meet Power Secretary, provide update on new testing facilities

  Officials of ERDA (Electrical Research & Development Association) recently met the newly appointed Power Secretary, Alok Kumar, and updated him on various ongoing projects at ERDA. In particular, ERDA officials informed Alok Kumar about the recently Read more

Sterlite

Sterlite Power completes reconductoring project ahead of schedule

Sterlite Power recently announced that it has successfully upgraded the capacity on the 132kV Hatia-Kamdara transmission line in Jharkhand, five months ahead of schedule. The 61.6-km long transmission line was upgraded as the Kamdara substation was choking under excess Read more