The planned addition of transmission lines in the ongoing fiscal year FY23 has been set at a little over 21,000 ckm, which is nearly 10 per cent higher than the comparable level for FY22.
The latest report of Central Electricity Authority states that the planned addition of transmission lines during FY23 is 21,098 ckm – 9.6 per cent higher than the 19,255 ckm planned for FY22.
It may be mentioned that in FY22, the actual addition of transmission lines stood at 14,895 ckm, implying target achievement of just 77.4 per cent.
Over the past few years, the target achievement has been erratic. In FY20, for instance, only 11,664 ckm of new transmission lines could get commissioned as against the planned 23,621 ckm. This gave rise to an achievement ratio of less than 50 per cent.
Most of the lines planned for completion in FY20 spilled over to FY21. With the result, FY21 saw the commissioning of 16,750 ckm of lines that was in fact 6.1 per cent higher than what was planned (at 15,791 ckm).
It is also worth observing that this addition of 16,750 ckm worth of transmission lines in FY21 has been the highest annual achievement in recent history.
Returning to the targeted 21,098 ckm of lines in FY23, here are some observations:
The fiscal year FY22 that closed on March 31, 2022, saw the addition of 14,895 ckm of transmission lines. Unlike what is foreseen in FY23, the performance of 765kV lines was encouraging in FY22 with a total addition of 4,933 ckm representing a third of the year’s total achievement. State government utilities, mainly through 220kV lines, accounted for 60 per cent of the total addition in FY23.
Also Read: Substation capacity addition target up 17 per cent in FY23